Calculate the batch cost, then divide by metres

Processing cost per metre = total processing cost for the batch ÷ cutting length. Start by adding machine time, gas, consumables, setup and any separately charged labour, counting each cost once.

Hypothetical example, using assumed currency units rather than market rates: machine time 2 h × 50 units/h = 100; gas 20; consumables 10; setup 30; separate labour 40. Total processing cost = 200 units. If the batch executes 100 m of cutting path, cost = 200 ÷ 100 = 2 units per executed metre. Assume the 50-unit hourly rate includes power and depreciation but excludes the other listed items, and setup is outside those 2 h. Raw material, tax and delivery are excluded.

Choose the length that answers your question: executed path metres for process use, or accepted delivered contour metres for the cost of usable output. For example, if the same assumed batch delivers 80 m of accepted contours, 200 ÷ 80 = 2.5 units per accepted contour metre. Keep these two measures separate.

InputUnit and boundaryCheck
Batch length Lm; choose L_cut or L_good as defined belowSame denominator definition and clear allocation for the same batch
Time T and machine rate rh and currency/h; list inclusionsIf power or labour is inside r, exclude it from separate terms
Gas G and consumables CTotal batch currency from measured usage or stated assumptionsDo not treat gas flow or consumable life as universal per-metre constants
Setup S and separate labour HBatch currency; identify included operationsDo not add setup again if already included in T
Comparable outputCost/m = (rT + G + C + S + H)/L, L > 0State material, cut quality, pierces, batch size, currency/date and exclusions

L_cut is the batch's executed cutting-path length in m, including scrap cuts; state how lead-ins, lead-outs and shared cuts are counted. It excludes non-cutting travel; record piercing separately as count N. L_good is the agreed drawing-based inner and outer cutting-contour length of accepted delivered parts, not sheet length or just the outside perimeter. State its lead-in/shared-cut treatment too. Record the drawing/program version and whether lengths are estimated or measured. Choose L = L_cut or L = L_good, with L > 0.

With L_good, all agreed processing costs incurred in the same batch, including scrap and rework, may be allocated to accepted delivered contour metres, each cost once. Name this the batch cost per accepted delivered contour metre. With L_cut, the result is cost per executed cutting-path metre. These are different indicators and must not be compared directly. Costs must belong to the same batch with clear allocation; numerator and denominator need not cover the same physical set of parts.

What the cost per metre has to include

The table is one way to allocate processing costs, not a universal list of separately billed charges. Here the machine-rate row includes depreciation and power by convention; record the actual inclusions, especially direct labour. Gas and consumable costs per metre are batch allocations, not fixed physical constants.

ComponentSymbolWhat drives itScales with
Machine timer x tHourly rate with depreciation and power by this table's convention; declare direct labour inclusionsCut length, thickness, quality class
Assist gasgGas type, purity and flowMaterial, thickness, quality class
ConsumableskNozzle and lens lifePierces, thickness, quality class
LabourlOperator time and handlingBatch, loading, inspection
SetupS / LProgramming and fixturing spread over the batchBatch length

M is the net cost of material put into this batch, including material losses, less the agreed remnant/scrap recovery credit applied once. If losses are already in that input-material amount, do not add them again. Processing costs of scrap/rework belong once in rT, G, C, S or H as applicable; do not add a complete scrap charge containing the same costs. For customer-supplied material, state the material exclusion and responsibility for losses. State whether post-processing, packing, transport and tax are included or separate.

Machine time is rate times time

T is the billed machine occupancy in hours within the agreed billing scope. List cutting, piercing, non-cutting travel, waiting and handling time, and state which enter T and whether setup is included. Piercing and travel may enter T without adding metres to L; N cannot be added to metres. Machine occupancy and labour person-hours are separate records, particularly with multiple operators or machines.

Small features, frequent pierces and corners can change time even at the same cutting length. Use the job's time breakdown rather than a universal piercing allowance. If rT already includes piercing time and a quote also has a piercing surcharge, ask what the surcharge covers; do not accumulate the same time cost twice.

Choose gas for the process and edge requirement

Nitrogen is commonly used for oxide-free fusion cutting and oxygen for reactive cutting; the validated process and required edge determine the route, rather than material name alone. [A1] Allocate G from this batch's gas usage or bill. For flow multiplied by gas-on time, use consistent units; gas-on time need not equal cutting time or T.

Consumables are a per-metre cost too

Consumable allocation may use replacement cost divided by useful-life metres only when that life record and its length definition apply to the current conditions. Check maintenance records for nozzles and lenses rather than assuming a universal effect of thickness or quality class.

Labour and setup have to be spread over the batch

H is a monetary amount, not hours: separately billed person-hours multiplied by the applicable labour rate. Include only labour not already inside r, S or another term. Identify programming, nesting, fixturing, first-part checks, loading, unloading, inspection and packing. A fixed setup amount is spread over more metres only if the same setup can be reused; it does not guarantee batch savings.

How cost components add up per metre

For the same batch, C_proc = rT + G + C + S + H; processing cost/m = C_proc/L. C is consumables, not the processing total. Let t = T/L (h/m), g = G/L, k = C/L and l = H/L (currency/m); r is currency/h and S is batch currency. Then C_proc = r t L + g L + k L + l L + S; cost/m = r t + g + k + l + S/L. t uses machine occupancy within the agreed billing scope, including piercing/travel only as specified. State whether r includes direct labour; if it does, H covers only additional labour outside r, S and other terms. If T includes setup, S contains only separate setup costs not already in rT.

Optionally, C_with_material = C_proc + M and its cost/m = C_with_material/L. With L_good, this allocates the same batch's net input-material cost, including losses and the single recovery credit, to accepted delivered contour metres; it is not material cost of accepted parts alone. A supplier's accepted-parts-only material amount is another basis and cannot be mixed with this one. State all other included/excluded items before comparing totals. Cost allocation is not selling price; profit, tax and delivery terms require the actual quotation.

Why the hourly rate alone misleads

  • A lower hourly rate can still give a higher cost per metre, depending on time and the other batch costs.
  • A higher rate can give a lower cost per metre if actual time and other inputs support it.
  • Setup allocation depends on the batch and whether preparation can be reused.
  • Thickness and edge requirements can affect several inputs; recalculate from the stated job data.
  • A rate alone does not identify gas, consumable, material or labour inclusions.

For comparison, request the drawing/contour revision, material grade/coating/thickness and supplier, quantity and repeat batches, L definition/source, lead-in/shared-cut treatment, pierce count, time breakdown and estimated/measured status, gas route and usage source, agreed edge requirements, post-processing, material/loss/recovery allocation, rate inclusions, currency, date, tax and delivery scope. Unknown process inputs are for the actual processor to clarify. Where ISO 9013 applies, agree the relevant edge characteristics and quality ranges; a standard number or a supposedly higher class alone is not an acceptance requirement.

If only a total price is available, establish at least L and its definition, the total and its inclusions/exclusions, currency, tax and date. Mark missing time or gas details as not itemised. Compare only the confirmed scope; do not infer efficiency or cost structure from the total.

How to reduce cost per metre without cutting quality

  • Review nesting for material utilisation; it does not automatically reduce cutting length or pierces. Only reviewed path changes, such as suitable shared cuts, may do that.
  • Group compatible material and thickness only where the same setup can be reused.
  • Agree the edge requirements the part needs with the authorised party.
  • Have the authorised party review contour features against function before changing the drawing.
  • Consider more batch metres only with reusable setup; recalculate at the same requirements and scope without promising savings.

Summary

Define the denominator, the agreed time scope and the batch cost allocation; count each cost once. Keep executed-path and accepted-delivery contour metrics distinct. Use the two cards for process and edge-quality questions, and compare quotations only within their stated scope.