Start with the machine you ordered

Check five areas at handover: the machine and options supplied, documents, safety functions, mechanical condition, and performance on representative parts. Compare each with the order and agreed acceptance criteria, then record what passed and what needs correction.

Use the agreed checks when discussing the configuration and acceptance plan for Press brakes.

Check ordered equipment, documents and identification

Compare the nameplate model, serial number, power supply and working length with the order. Check the ordered options and document list: manual, wiring diagram, spare parts list and hydraulic or pneumatic diagrams where those systems are fitted. Identify the ordered punches and dies and record the control software version. Record missing or different items against the order.

Verify safety functions for the delivered configuration

Check protective devices, emergency stops, punch retention, earthing, guards and enclosures against the supplied configuration and applicable design basis. Include two-hand control where fitted and for its intended mode. Have competent personnel validate the functions using the manufacturer’s documented procedure, and retain the procedure reference, configuration, results, responsible person and date.

Geometry and mechanical checks

Use the agreed methods, conditions and limits to record table/ram geometry, punch/die alignment and seating, and backgauge positioning. Record leakage checks for hydraulic or pneumatic circuits where fitted, and observations of abnormal noise, vibration or overheating under the agreed run conditions. A general description such as “parallel” does not replace measurements and an agreed acceptance basis.

Functional and bend test

Have the designated personnel complete and record the approved functional checks, including axis referencing and the response of the stroke and backgauge to the program where applicable. Keep these results separate from the forming test. Record the machine, tools and program revision used; a demonstration that the machine bends is not a complete acceptance result.

Agree test pieces, measurement positions and repeatability checks

Select representative test pieces and measurement positions before testing. A full-length piece or a 90° piece can be an agreed example where appropriate to the purchase scope and test plan; neither is a universal mandatory test. Use the intended grade, condition, batch and actual thickness. Record every agreed position and each separately identified repeat specimen under the agreed conditions, not only the best reading.

Assess machine-axis positioning by its agreed inspection method separately from formed-part results. The same commanded ram depth alone does not prove forming repeatability: material, tools, setup and measurement also affect the result. Use the trial-bend guide.

If the same purchase includes a shear or cutting machine, define its own applicable functional and cut-edge checks and records separately. Replacing a bend test with an edge check does not make the press-brake test procedure transferable to another machine.

Prepare the test sheet and choose the standard edition

Agree which checks belong to factory acceptance and which belong to site acceptance after installation. State the stage above the evidence sheet and identify deferred items explicitly. An unknown requirement or an untested item remains open. Select applicable standard references and editions using the Standards index.

FieldRequired entry
ReferenceOrder and drawing revision, machine serial number, standard edition and test item
SetupMaterial batch and actual thickness, tools, program revision and machine condition
MeasurementCharacteristic and datum, agreed limit, instrument identity, every result and sample count agreed before testing
DispositionPass, fail or not tested; original evidence link; owner and date for correction; retest result

Choose the worksheet section for the standard and edition agreed in the contract. GB/T 14349-2011 remains current until GB/T 14349-2026 takes effect on 2027-02-01. For the 2026 edition, agree the applicable I/II/III grade. Enter limits from the selected formal standard and contract in the blank cells; keep editions separate.

Keep settings, all readings and traceable evidence

Keep each check and its requirement, method, instrument identity, datum, units and all readings linked to the machine and specimen IDs. For angle measurements, record the angle convention and loading state; keep all agreed positions along the specimen. Record the agreed temperature measurement object, such as the machine during the run or the ambient air, with its reading and time; identify specimen temperature separately if the plan requires it. No universal temperature or stabilisation time is specified here.

Retain the order/drawing and program revisions, tool identities, specimen or its traceable evidence, original results and both parties’ recorded decisions. Keep applicable cut-edge records with their machine identity. Preserve open-item actions, owners and target dates; do not replace raw readings with a summary pass.

Resolve or record open items before signing

Keep failed, untested and site-deferred items visible, with the agreed action, responsible person, target date and evidence needed for recheck. Record the retest result and authorised disposition before closing an item. Sign a record that accurately states the acceptance status and remaining items. Delivery and payment consequences follow the parties’ agreement.